From no mud to this in six days. |
This blog is all about the Tamar sailing barge Shamrock. She has been around since 1899 and still going strong.
Monday 4 September 2017
Proposed Haul Out Day
After consulting the tide time tables the spring tide of Friday 6th October has been pencilled in as Shamrock's haul out day. This will allow time for the slipway track to be completed with the last two sections needing to be cut to their respective sizes and laid. Once completed Shamrock's cradle can be moved to the bottom of the slipway track to check it rolls freely and gauge the minimum tide height required to float Shamrock onto the cradle. The amount of silt that the river Tamar deposits on the slipway also means that it will need to be cleaned at least twice more before haul out day, once before laying the final sections of track and the day before haul out. Both of Shamrock's masts are also scheduled to be lowered and removed before the move.
Subscribe to:
Post Comments (Atom)
No comments:
Post a Comment